Sign up USA
Proactive Investors - Run By Investors For Investors

Lydian International's Amulsar gold mine on track and on budget

As at May 31, project commitments totalled $213 mln, the firm said.
Lydian International's Amulsar gold mine on track and on budget
Production at Amulsar is expected to begin in 2018 - Armenia's largest gold mine, with an estimated resource containing 3.5 million measured and indicated gold ounces and 1.3 million inferred

Lydian International Inc (TSE:LYD) said construction of its huge Amulsar gold mine in Armenia was on schedule and budget, with 58% of initial capital now spent.

As of the end of May this year, project commitments totalled $213 mln, the company revealed.

Access roads are now complete, while site earthworks continues to be the priority.

Work is complete  on the adsorption desorption refining (ADR) plant platform, the construction warehouse platform, and the heap leach facility (HLF) temporary sediment dam.

Work has kicked off on the platform for the crushing and screening plant and in other areas at higher elevations.

Machinery giant Caterpillar (NYSE:CAT) is ahead of schedule in producing the primary mine mobile equipment, and initial deliveries are expected to begin in late July.

The mining fleet for Amulsar will include, among other things, 19 Caterpillar 789D 180-tonne-capacity haul trucks, one 994 front-end loader and two  6040 hydraulic shovels. A training simulator has been purchased to train operators.

Lydian's  present and chief executive Howard Stevenson told investors:  "We are pleased with the progress of construction to date and look forward to achieving additional significant milestones through the summer.

"As construction continues to accelerate and employment approaches 1,300 workers later this year, we continue to enhance our safety programs and sustainability management systems to ensure the well-being of our employees, contractors, the environment and all of our stakeholders."

For the rest of 2017, Lydian says it expects to achieve the following significant milestones:

  • Complete major earthworks for the HLF, mine haul road and barren rock storage facility
  • Complete civils for all components of site infrastructure and equipment
  • Erect buildings for the material handling system and the ADR plant
  • Fabrication and delivery to site of major components of mechanical and electrical equipment
  • Commence installation of mechanical and electrical equipment
  • Fabrication, delivery to site and assembly of the mine mobile fleet
  • Finalize biodiversity offset boundaries
  • Hiring and training of staff for mine operations and the processing plant
  • The cost of the Amulsar gold project has been estimated at US$369.9 million, so the project is well on its way now.

Shares added 4.84% in Toronto to stand at 32.5 cents.

Giles_55af4ddca6481.jpg
Why Invest In Lydian International Ltd.? Read More Here

Register here to be notified of future LYD Company articles
View full LYD profile View Profile

Lydian International Ltd. Timeline

Newswire
February 09 2017
Newswire
November 14 2016

Related Articles

no_picture_pai.jpg
April 12 2017
Pan African hopes to be in production at Elikhulu in the final quarter of next year.
Gold---usable.jpg
November 02 2016
Caledonia Mining is now well into an expansion plan that could boost gold production
shutterstock_157865516-001_580d4502e2d04.jpg
October 23 2016
These mid-program results demonstrate the potential the Wa Gold Project has to host shallow gold mineralisation.
Copyright © Proactiveinvestors.com, 2017. All Rights Reserved - Proactive Investors North America Inc., Proactive Investors LLC

Market Indices, Commodities and Regulatory News Headlines copyright © Morningstar. Data delayed 15 minutes unless otherwise indicated. Terms of use