02:00 Thu 12 Nov 2020
Premier Oil PLC - Trading and Operational Update

Premier Oil plc
"Premier" or the "Company" or the "Group"
Trading and Operational Update
Premier today provides a Trading and Operations Update for the 10 months to
Highlights
§ Proposed merger with Chrysaor announced, creating the largest
- Combined production to the end of October of 237.5 kboepd
- Creditor support received. Transaction completion expected by end Q1 2021
§ Premier's production averaged 62.5 kboepd for the 10 month period. Full year production guidance is revised to 61-64 kboepd to take into account recent constraints at Catcher
§ Solan P3 brought on-stream in September as planned, production capacity of more than 10 kbopd from the field in the near term
§ Tolmount: platform installed and drilling of the four development wells commenced. First gas forecast for Q2 2021, adding 20-25 kboepd (net) once at plateau
§ Significant growth optionality maintained:
- Zama (
- Tuna (
- Highly encouraging results from new 3D data sets in
§ Forecast 2020 opex (ex-lease costs) unchanged at
§ Net debt of
"The merger with Chrysaor, which will create a Combined Group with diversity, scale and balance sheet strength, is progressing to plan. We now have creditor approval and we expect to publish the prospectus in December, with completion on track for the first quarter of 2021."
Enquiries
Premier Oil plc Tel: 020 7824 1116
Tony Durrant (CEO)
Richard Rose (Finance Director)
Camarco Tel: 020 37575 4983
Billy Clegg, Georgia Edmonds
Notes to Editors
Terms defined in the announcement of 6 October shall have the same meaning in this announcement.
Production operations
Group production averaged 62.5 kboepd to the end of October. Summer maintenance programmes were safely completed. The additional logistical complexity introduced by COVID-19 continues to be successfully managed.
Premier's operated Catcher Area, the Group's largest producer, averaged 26.5 kboepd (net, Premier operated 50 per cent) to the end of October. The August shutdown was completed successfully and plateau production was re-established in September, with the Varadero infill well (VP1) now also online. However, in late September, production was constrained due to the produced water plant being offline while a build-up of calcium naphthenate was removed. This work took longer than originally envisaged and the produced water plant was reinstated in early November.
On 9th November, there was a fire in the electrical equipment (HVAC switchboard) in the main store room on board the FPSO which was swiftly and safely extinguished. No personnel were injured. The facilities were made safe and production shut in. BWO, the operator of the Catcher FPSO, is working to reinstate the HVAC which would enable production to restart within the next week.
The third producer (P3) at Solan was successfully brought on-stream on 15 September. The well free-flowed at rates of up to 9.5 kbopd, demonstrating the successful targeting and delivery of the reservoir by the subsurface and drilling teams. Production was choked back from these levels to minimise excess flaring while the fuel gas and power system are recommissioned. Production from the P3 well, with the ESP online, is expected to reach rates in excess of 10 kbopd (Premier 100 per cent).
The Elgin Franklin Area produced 6.8 kboepd (net, Premier 5.2 per cent), which was ahead of budget. Production continues to be supported by high operating efficiency and an active rig programme with the F13 well brought on-stream in October.
As previously announced, Premier, together with its joint venture partners decided to cease production from certain mature UK fields not generating positive cash flows in the current environment. At Huntington, which ceased production in April, the first phase of the decommissioning programme was substantially completed with the sailaway of the FPSO and recovery of the riser systems. The second phase, which will entail recovery of the subsea equipment and remaining mooring system, is scheduled for 2022. Final production from the operated Balmoral Area, which surpassed two years without a lost time injury in September, is planned for
Production from Premier's operated Natuna Sea Block A fields in Indonesia averaged 12.2 kboepd (net, Premier 28.67 per cent interest), in line with budget. Singapore demand for Premier's Indonesian gas was stable for the period, averaging around take or pay levels under Premier's gas sales contracts, GSA1 and GSA2. Natuna Sea Block A captured a 55.8 per cent market share of GSA 1, materially above its contractual share of 52.5 per cent. Government and joint venture approvals have been received for the planned 2021 infill drilling campaign to help maintain deliverability from Natuna Sea Block A.
In Vietnam, Premier's operated Chim Sao field produced 8.7 kboepd (net, Premier 53.125 per cent interest), benefitting from high uptime of over 90 per cent and four well intervention campaigns, with the final campaign being completed in October. In addition, Premier is in the process of securing the necessary regulatory approvals for a two well infill programme in 2022. Demand for Chim Sao crude remains robust with cargoes sold during the period realising an average premium to Brent in excess of
Development
The 500 BCF (gross) Tolmount development (Premier-operated, 50 per cent interest) remains on track for first gas in Q2 2021. The platform, which left the yard in Italy in September, was successfully installed over the Tolmount field in the UK Southern Gas basin during October. A shallow gas survey pilot hole has been successfully completed and the first of the four firm development wells was spudded by the Valaris 123 rig on 10th November. The Tolmount field is expected to add 20-25 kboepd (net, Premier 50 per cent) to Group production once at plateau rates.
On the proposed Tolmount East development, Premier is now in final negotiations with its selected contractors ahead of making a final investment decision on the project. Once on-stream, Tolmount East will help extend plateau production from the Tolmount Area. In addition, in September, Premier was awarded two licences directly adjacent to its Tolmount Field Development Area and is in the process of maturing a number of leads and prospects which, in the success case, could be developed via the Tolmount infrastructure.
In Mexico, negotiations between the Block 7 partners and PEMEX regarding the Zama field development plan and the unitisation of the Zama field are progressing and are expected to conclude in Q1 2021. FEED on the Zama project scheme (two platforms plus FSO) is reaching a conclusion and pending progress on the unitisation and other approvals a final investment decision would be made later in 2021.
In the Falkland Islands, the 250 mmbbl Sea Lion Phase 1 project is currently on hold. In the meantime, Premier continues to work with the Falkland Islands Government (FIG) on licensing, fiscal and regulatory matters. The proposed farm-out of the Sea Lion licences to Navitas is subject to FIG and, pursuant to the Merger Agreement, Chrysaor's approval.
Exploration and appraisal
In Indonesia, the farm out agreement with Zarubezhneft for a 50 per cent interest in the Tuna discoveries was signed in September. Premier and Zarubezhneft are now in the process of securing Indonesian government approval for the farm out agreement and a one year extension to the Tuna PSC to
Premier continues to mature its highly prospective portfolio of opportunities on the new 3D data sets in Mexico and the
Finance
Premier's operating costs and lease costs averaged
Premier now forecasts 2020 full year total capex, including abandonment expenditure, of
Net debt as at the end of October was
Board and management changes
As previously announced Tony Durrant will step down as Chief Executive by the end of the year. Richard Rose will be the interim Chief Executive until completion of the Transaction, in addition to his current role as Finance Director. Stuart Wheaton, currently Chief Operating Officer, will assume the role of interim Deputy Chief Executive.
Proposed merger with Chrysaor
In October, Premier announced the proposed merger of Premier and Chrysaor Holdings Limited and the reorganisation of Premier's existing financing arrangements. Premier has subsequently received the requisite level of support from each class of its creditors for the Transaction. As a result, the merger agreement between Premier, Harbour, funds managed by EIG and Chrysaor was released from escrow on 2nd November.
Premier plans to publish a prospectus, which will include an independent valuation of Chrysaor's 2P reserves, and a shareholder circular by the end of the year. The shareholder circular will include details of the shareholder meeting to approve the Transaction, which is anticipated to take place in January.
Premier will launch the Court-approved restructuring plan processes, to implement the repayment and cancellation of its existing debt, through the issuance of a practice statement letter, immediately after the Prospectus for the Transaction is published.
The Transaction is expected to complete by the end of Q1 2021.
Chrysaor update
The following information has been provided by Chrysaor for the period to the end of October.
Chrysaor's production averaged 175 kboepd to the end of October. This was split 84 kboepd from liquids and 91 kboepd from gas; operated assets 103 kboepd and non-operated assets 72 kboepd. Chrysaor's full-year forecast remains unchanged and in the range of 170-180 kboepd, with reduced levels of drilling and rephrasing of operational activities offset by a shortening of planned shutdowns.
Chrysaor's operated drilling programme, which had been suspended in March, resumed in September with the Valaris 120 heavy duty jack up over the Jasmine wellhead platform to drill the Joanne Chalk S16 well. This well has been successfully drilled to depth and completion operations continue with first production expected before the year end. The Transocean Paul B Lloyd Jnr also commenced drilling operations in September and has successfully drilled the Greater Britannia Area - Callanish F5 well to depth. First production from this well is expected in Q1 2021.
Operating costs (including net tariff costs) for the period were
Chrysaor benefits from a significant hedge programme with c. 85 per cent of its Q4 2020 oil production hedged at
Additional information on Chrysaor can be found at www.chrysaor.com.
Appendix
Premier Group production breakdown
kboepd | 1 January - | 1 January - |
Indonesia | 12.2 | 11.0 |
Pakistan1 | - | 1.4 |
UK | 41.6 | 55.3 |
Vietnam | 8.7 | 11.7 |
Total | 62.5 | 79.4 |
1 Sold as at
The information contained within this announcement is deemed by Premier to constitute inside information as stipulated under the Market Abuse Regulation. By the publication of this announcement via a Regulatory Information Service, this inside information is now considered to be in the public domain. The person responsible for arranging for the release of this announcement on behalf of Premier is Andy Gibb (Group General Counsel).
RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
NO INVESTMENT ADVICE
The Company is a publisher. You understand and agree that no content published on the Site constitutes a recommendation that any particular security, portfolio of securities, transaction, or investment strategy is...
FOR OUR FULL DISCLAIMER CLICK HERE