RNS Number : 8447R
Zephyr Energy PLC
24 August 2026
 

Prior to publication, the information contained within this announcement was deemed by the Company to constitute inside information as stipulated under the UK Market Abuse Regulation. With the publication of this announcement, this information is now considered to be in the public domain.

 

 24 August 2026

Zephyr Energy plc

("Zephyr" or the "Company")

 

Paradox Project update

 

Zephyr Energy plc (AIM: ZPHR) is pleased to provide an update on current activity on its project in the Paradox Basin, Utah, U.S. (the "Paradox project"). 

 

Highlights:

 

·    Zephyr's board of directors (the "Board" or the "Directors") has elected to fund additional engineering and well work to prepare for a higher production rate during the initial phase of the project's development.

o  This is supported by the Board's confidence that the necessary regulatory approvals needed for up-rating the operating pressures of Enbridge-operated 16-inch pipeline will be obtained; and

o  Zephyr's additional work is progressing in parallel with the Enbridge-led regulatory approval process, and will be funded out of the Company's existing cash resources.

 

·    Engineering work is underway to design a modular gas processing system with up to 15 million standard cubic feet of gas per day (mmscf/d) of production capacity.  Gas will be initially supplied by the State 36-2 LNW-CC-R well (the "State 36-2R") and the Federal 28-11 well.

o  Expense related to "well work" (or "workovers") involves preparations to allow for existing wells to return to production in a timely manner.

 

·    Zephyr has also high-graded new well locations for follow-on drilling. Locations and permitting details will be announced as and when well planning efforts are finalised. Plans for the tie in of the State 16-2 well will be detailed after first gas is achieved.

 

·    Enbridge's operation to excavate and visually inspect four short sections of the existing 16-inch pipeline is ongoing, with no concerns or safety issues noted to date.

 

Colin Harrington, Zephyr's Chief Executive, said: "The successful completion of the Enbridge in-line inspection provided the Board with confidence that the up-rating of operating pressures required for the pipeline to accept Zephyr's increasing gas volumes will not result in any further operational hurdles.

 

"The Board has also gained confidence that the Enbridge-led regulatory approval process will conclude in a satisfactory manner.  The Board has therefore approved an allocation of funding for additional engineering (related to gas processing) and well work operations, with a goal to increase initial processing capacity up to 15 mmscf/d - a significant increase over earlier base case estimates of 5 mmscf/d. This work will be fully funded from the Company's existing cash resources.

 

"Initial gas volumes would be provided by the State 36-2R and the Federal 28-11 wells, with additional production from new and existing wells to follow as cash flow, planning and regulatory approvals allow.

 

"Our aim is to progress operational work in parallel with the Enbridge-led regulatory approval process, in order to expedite the timing for first gas and commercial production.  While the timeline for Enbridge's approval process remains pending, Zephyr's goal is to be prepared to deliver first gas and commercial production as soon as possible once approvals are secured.

 

"The Company also continues to progress both the potential farm-out and the proposed US$15 million commodity purchase agreement (as announced on 27 July 2026). Further updates will be provided in due course."

 

Background

 

In relation to the Paradox project gas transportation, Enbridge continues to execute on its workstream to obtain the necessary regulatory approval needed to export Zephyr's natural gas through its 16-inch pipeline and into the Williams-operated, Northwest Pipeline system.

 

As indicated previously, regulatory approval remains a critical item for Zephyr to achieve first gas and commercial production from the Paradox project. To date, Enbridge has successfully completed a mandatory in-line inspection of the pipeline, and the process of excavating and visually inspecting four short sections of pipeline is well underway.  Enbridge views such inspections as routine and they are not considered a risk to achieving first gas.  All inspection work on the 16-inch pipeline is being funded by Enbridge.

 

Zephyr is highly confident that regulatory approval for gas export will be granted, although the exact timing for such approval remains uncertain. The Company will continue to keep shareholders updated as Enbridge completes its inspection process and the timing for the regulatory approval process becomes better defined.

 

In the interim, the Board has elected to fund additional engineering and operations work to prepare for the initial phase of commercial production. Detailed engineering work related to design of a modular gas processing system with up to 15 mmscf/d of production capacity is underway, with gas expected to be initially supplied by the State 36-2R and the Federal 28-11 wells. Well work to equip, tie-in, and return the 36-2 and the 28-11 wells to production will commence after the engineering work and final processing design has been completed.

 

The Company has also high-graded future well locations for follow-on drilling, and will announce locations and permitting details when well planning efforts are finalised.

 

The State 36-2R well was drilled and production tested by Zephyr in 2025. The production test achieved a peak flow rate of 2,848 barrels of oil equivalent per day, with no material drop in bottom hole pressure, and without the use of any fracture stimulation, suggesting that the well ranks in the top 6% of gas wells across the Lower 48 U.S States.

 

The Federal 28-11 well was drilled in 2008, and was subsequently shut-in due to pipeline and infrastructure constraints. Prior to shut-in, the well produced over 0.36 billion cubic feet of natural gas and circa 93,000 barrels of oil. The well was acquired by Zephyr in 2022 (as announced on 22 September 2022). In 2023, the Company briefly and successfully recommenced production in order to understand the well's potential to contribute to future field production.

 

 

 

Contacts

Zephyr Energy plc

Colin Harrington (CEO)

Chris Eadie (Group Finance Director and Company Secretary)

 

 Tel: +44 (0)20 3475 4389

Allenby Capital Limited - AIM Nominated Adviser

Jeremy Porter / Vivek Bhardwaj

 

 Tel: +44 (0)20 3328 5656

 

Turner Pope Investments - Joint-Broker

Guy McDougall / Andy Thacker 

 

Canaccord Genuity Limited - Joint-Broker

Henry Fitzgerald-O'Connor / Charlie Hammond

 

Celicourt Communications - PR

Mark Antelme / Kristina Qevani

 Tel: +44 (0)20 3657 0050

 

 

Tel: +44 (0)20 7523 8000

 

 

 

Tel: +44 (0) 20 7770 6424

 

 

Notes to Editors

Zephyr Energy plc (AIM: ZPHR) is a technology-led oil and gas company focused on responsible resource development in the Rocky Mountain region of the United States.

Its flagship operated asset is the circa 70,000-acre Paradox project in Utah.  An independent 2025 Competent Persons Report by Sproule International of the Company's White Sands Unit (20,000 acres) confirmed 2P reserves of 35.3 million barrels of oil equivalent ("boe") and total recoverable resources of 74.2 million boe within the White Sands Unit.

Zephyr also holds a portfolio of non-operated production interests across the Williston and other Rocky Mountain basins, supported by a US$100 million strategic partnership designed to accelerate growth and enhance cash flow.

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.

RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
 
END
 
 
UPDEASPLASLKEEA
NO INVESTMENT ADVICE

Proactive Investors is a publisher of financial news and information. No content in this record, or published on the Proactive Investors website (the "Site"), constitutes a recommendation that any particular security, portfolio of securities, transaction, or investment strategy is suitable or advisable for any specific person. No content is tailored to any specific person's needs, objectives, or financial situation.

Proactive Investors is not a registered investment adviser or broker-dealer and does not provide personalized investment advice. Nothing in this record constitutes investment advice or a recommendation to buy, hold, or sell any security. None of the information providers or their affiliates will advise you personally concerning the nature, potential, advisability, value, or suitability of any particular security, portfolio, transaction, or investment strategy. Any decision to buy, sell, or hold a security should be made only after consulting an appropriately qualified, licensed financial adviser and reading all relevant offering documentation.

This record, and any record we publish by or on behalf of our clients, should not be construed as an offer or solicitation to buy or sell any product or security. Our content is independent financial journalism, produced in a neutral, objective style with full source attribution.

In accordance with the Federal Trade Commission's guidelines on material connections, Proactive Investors discloses the following: we may receive cash or, in some cases, equity compensation from companies whose news is distributed through our platform. This compensation is for news distribution and media services, not for editorial content or coverage decisions. Where Proactive Investors has a commercial relationship with a company covered in this record, that relationship is disclosed within the article. Any such relationship does not determine, influence, or shape the editorial content produced. Where we receive equity compensation, such securities are held independently by a third-party broker and sold at the broker's discretion.

The Site may contain opinions from time to time regarding securities mentioned in other products, including company-related products, and those opinions may differ from those obtained through another Proactive Investors product. Opinions and commentary reflect the views of the named author at the time of writing and are subject to change without notice.

Price and other data is supplied by sources believed to be reliable. Any calculations are made using such data. Neither the data nor the calculations are guaranteed by those sources, by Proactive Investors, by the information providers, or by any other person or entity, and may not be complete or accurate.

From time to time, reference may be made in our marketing materials to previously published articles or opinions. Such references may be selective, may reference only a portion of an article, and are likely not to be current. As markets change continuously, previously published information and data may not be current and should not be relied upon.

FOR OUR FULL DISCLAIMER CLICK HERE

Iofina, Tertiary Minerals, Quantum Helium, Zephyr Energy, Tower Resources,...

Iofina PLC (AIM:IOF, OTC:IOFNF) jumped over 4% in early trading after boosting output at its IO#11 plant with a new brine source. It said the extra supply should lift crystalline iodine production there by 50%. Read more Tertiary Minerals PLC (AIM:TYM, OTC:TTIRF, FRA:TMU) says final...

on 08/24/2026

7 min read