Significant Progress Towards Project Development
Capital Metals (AIM: CMET), a mineral sands company approaching mine development stage at its high-grade Taprobane Minerals Project in
Highlights
· Engineering Studies Towards Stage 1 FID Largely Complete:
o Fixed construction plant and services lump sum price negotiated with Mineral Technologies.
o Access Engineering study completed covering plant construction and site civil works.
o Site access study completed with preferred option selected.
o Hydrogeology study completed for the Initial
o Mine planning work underway on the expansion of the IMA following successful drilling.
· Further Material Reduction in CAPEX: The ongoing process of cost refinement has resulted in a decrease in Stage 1 CAPEX from
· Building Community Support: Proactive and focussed community educational and support initiatives continue to strengthen the Company's social licence to operate.
· Coastal Regeneration Centres: Plans have been finalised for the first of several nurseries along the Project strike length, with construction and operational activities underway on the first site.
· Growing Sri Lanka Team: The in-country team has expanded with the addition of key finance, compliance and environmental leadership roles.
· EL199 Environmental Impact Assessment ("EIA"): in addition to the already approved EIA and the 2 Industrial Mining Licenses ("IML") in the northern EL168 area, a technical meeting has been scheduled with key approving agencies following submission of the EIA for the southern exploration licence (EL199).
· Mineral Separation Plant ("MSP") Studies: Mineral Technologies engaged to undertake a concept study for the potential acceleration of the MSP stage, with land access processes having commenced.
· National Minerals Policy: As announced,
· Project Funding Advancing: Ongoing discussions for debt as well as expressions of interest from strategic industry investors and offtakers, being run in parallel with final government approvals.
Engineering Studies Towards Stage 1 FID Largely Complete
The Company is pleased to advise that it has negotiated a fixed lump sum proposal from Mineral Technologies for the engineering, procurement and supply of key plant and equipment, including the Flex Series spiral plant. The Company has also received completed engineering design, cost estimates, and project schedules from Access Engineering. These workstreams provide increased certainty on capital costs and materially de-risks the project, contributing to a further reduction in CAPEX. A diagram showing the Wet Concentrator Plant Layout is shown in the appendix below (Figure 2) and is available on the Presentations page of the Company's website.
The International Center for Sustainable Built Environment Pvt Ltd ("ICB") was engaged to study site access options. Following completion of this study, and assessment against key technical, environmental and commercial criteria, a preferred access route has been selected. The Company has entered into the next stage of service agreements with ICB to support the Company in obtaining the relevant approvals.
The hydrogeology study has been completed, with this work supporting a lower impact and lower cost water management strategy. The study also supports proposals for mining below the water table.
Further Material Reduction in CAPEX
Following completion of the engineering studies outlined above, the Company has received detailed design, equipment specification and vendor pricing inputs which have enabled a refinement of the capital cost estimate and a reduction in line-item contingencies. The transition from preliminary study assumptions to more defined engineering parameters has materially improved cost accuracy across key workstreams, including processing plant design, materials handling and associated infrastructure.
Importantly, the fixed lump sum proposal from Mineral Technologies provides a high degree of cost certainty in respect of the major plant and equipment components of the investment, materially de-risking one of the most significant elements of Project CAPEX.
As a result of this increased engineering definition and commercial clarity, the estimated initial CAPEX has reduced to
Building Community Support
The Company continues to foster strong relationships with local communities in
Facebook has been identified as a key platform for community communication and education. The Capital Metals Lanka Facebook page continues to perform strongly averaging over 400,000 viewers per month, with a growing follower base and consistently high engagement.
Feedback from the local community, government officials and political representatives has been increasingly positive, reinforcing the Company's view that the vast majority of the community is supportive of the Project. During the Board's recent visit to the Project area, two significant CSR initiatives were undertaken. The first was the highly successful Capital Metals Cricket Cup, with over 40 teams from across the Project area participating. Our director and Sri Lankan cricket legend,
Coastal Regeneration Centres
The Company has finalised plans for the first Coastal Regeneration Centre ("CRC"), which will be one of several nurseries designed to support progressive rehabilitation, environmental management and community engagement activities associated with the Project. Construction is now underway, with initial operational activities commencing in parallel. The CRCs will serve as a practical demonstration of the Company's commitment to responsible mining and sustainable coastal management, while also providing local jobs and a platform for stakeholder education and training.
The CRCs will function as dedicated nurseries and holding facilities for translocated plants, rescued species and propagated native seedlings required for restoration. Baseline ecological surveys will be undertaken before mining to document vegetation and identify species suitable for translocation. Selected plants will be carefully removed with intact root balls and relocated to the CRCs, while topsoil (including the soil seed bank) and organic matter will be separately stored for later reuse. The CRCs will include greenhouse facilities, irrigation systems, composting areas, plant storage and trained staff to propagate creepers, herbaceous cover and woody species needed to stabilise restored dunes and rebuild soil quality.
Over time, the CRCs will provide an opportunity not only to restore but to measurably enhance the extraction area by improving soil structure, increasing native biodiversity and strengthening long-term coastal resilience. The CRCs will use modern expertise, technology and processes gained from the Australian mineral sands industry.
Figure 1: Coastal Regeneration Centre Layout Drawing (also available on the Presentations page of the Company's website at: https://capitalmetals.com/our-investor-relations/presentations/)

Growing Sri Lanka Team
The Company is pleased to announce the appointment of three key personnel to further strengthen its in-country capability in
Silojah Sivapathan has joined as Environment Specialist. A native Tamil speaker from the
Both Kishan and Silojah have joined the in-country leadership team.
Amasha Gunarathna has been appointed as Regulatory & Government Relations Executive, supporting stakeholder engagement and coordination with relevant government authorities as the Company advances through the approvals process. Amasha is an Honours Graduate Geoscientist with expertise in regulatory affairs and government coordination, with experience supporting compliance, documentation and field activities for mineral development projects, including having worked at the Geological Survey and Mines Bureau ("GSMB") of
These appointments materially strengthen the Company's technical, regulatory and governance capacity as it progresses toward FID.
EL199 Environmental Impact Assessment
The Company confirms that the EIA for EL199 was formally submitted to the relevant authorities in
The EL199 area represents an optimal location for additional mining areas, providing the opportunity to materially increase production capacity. Upon receipt of EIA approval, the Company will be positioned to apply for IMLs within the relevant grid areas, as it did with EL168.
Mineral Separation Plant Studies & Land Access
The Company has engaged Mineral Technologies for engineering and design works to progress the concept study for an MSP. The concept study scope includes:
· A collaborative workshop to align objectives and identify opportunities to reduce capital costs while delivering processing flexibility.
· Develop basic MSP process flow diagram.
· Develop a baseline 3D model of the MSP concept.
· Produce a factored Capital Cost Estimate (CAPEX) for the MSP with defined battery limits.
· Produce preliminary mechanical equipment list.
The study's deliverables are as follows:
· Preliminary process flow diagrams.
· CAPEX estimate with +/- 35% accuracy.
· Conceptual level 3D model based on the recommended process flowsheet.
· High level estimates of fuel consumption rates for the dryer and total power draw (kW).
The Company has formally requested the allocation of approximately 30 acres of land within the Hambantota Port district on which an MSP could be sited.
National Minerals Policy
The Company recently reported the publication of
The approval of the Policy was required before more focused discussions could take place with the appointed stakeholders, in particular the GSMB, to finalise the process to approve the additional mining licence and the clarification of what can be exported from
Project Funding Advancing
Capital Metals is in ongoing discussions with banks and other investors to provide project debt. The Company is also engaged in active discussions with preferred potential offtakers, with a focus on those that may also provide project equity or working capital funding. The recognised high quality of the Project's mineral products has attracted broad market interest, and counterparties have expressed positive interest in long-term supply arrangements.
The Company is prioritising offtakers prepared to provide upfront investment in equity or prepayments on offtake as an alternative source of funding. These discussions naturally need to be run in parallel with the processes to obtain the key final two approvals required for FID as the grant of the additional IML and the clarification of what can be exported will be preconditions for any financings.
Final Investment Decision ("FID")
The Company continues to work towards achieving a FID in order to commence construction before the end of Q2 2026, with an expected 9-12-month construction period until first production.
"The Company has continued to make strong progress towards FID, advancing key engineering, regulatory and stakeholder workstreams while further improving project capital efficiency. Engineering studies required for FID are now largely complete, including access, hydrogeology and construction planning studies, alongside negotiation of a fixed lump-sum price with Mineral Technologies for the plant and services.
Importantly, ongoing optimisation has delivered a further material reduction in Stage 1 CAPEX, reducing estimated capital expenditure to
Community engagement initiatives continue to strengthen local support, with construction underway on the first Coastal Regeneration Centre and expansion of the
Funding discussions with debt, offtake and strategic partners are advancing in parallel with permitting activities, with the grant of the additional IML and the clarification of what products can be exported being essential preconditions for any financings."
Investor Webinar
Capital Metals announces that the Company's Executive Chairman,
Investors can sign up to Investor Meet Company for free and add Capital Metals in order to attend the webcast via: https://www.investormeetcompany.com/capital-metals-plc/register-investor.
Investors who already follow Capital Metals on the Investor Meet Company platform will automatically be invited. Questions can be submitted pre-event via the Investor Meet Company dashboard up until
For further information, please visit www.capitalmetals.com or contact:
|
Capital Metals plc |
Via Vigo Consulting |
|
Vigo Consulting (Investor Relations) |
+44 (0)20 7390 0234 |
|
Strand Hanson Limited (Nominated Adviser) |
+44 (0) 20 7409 3494 |
|
Hannam & Partners (Broker & Financial Adviser) |
+44 (0)20 7907 8500 |
About Capital Metals
Capital Metals is a
Visit our website:
Follow us on social media:
LinkedIn: @Capital Metals plc
APPENDIX
Figure 2: Wet Concentrator Plant Layout Drawing (also available on the Presentations page of the Company's website at: https://capitalmetals.com/our-investor-relations/presentations/).

RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
Proactive Investors is a publisher of financial news and information. No content in this record, or published on the Proactive Investors website (the "Site"), constitutes a recommendation that any particular security, portfolio of securities, transaction, or investment strategy is suitable or advisable for any specific person. No content is tailored to any specific person's needs, objectives, or financial situation.
Proactive Investors is not a registered investment adviser or broker-dealer and does not provide personalized investment advice. Nothing in this record constitutes investment advice or a recommendation to buy, hold, or sell any security. None of the information providers or their affiliates will advise you personally concerning the nature, potential, advisability, value, or suitability of any particular security, portfolio, transaction, or investment strategy. Any decision to buy, sell, or hold a security should be made only after consulting an appropriately qualified, licensed financial adviser and reading all relevant offering documentation.
This record, and any record we publish by or on behalf of our clients, should not be construed as an offer or solicitation to buy or sell any product or security. Our content is independent financial journalism, produced in a neutral, objective style with full source attribution.
In accordance with the Federal Trade Commission's guidelines on material connections, Proactive Investors discloses the following: we may receive cash or, in some cases, equity compensation from companies whose news is distributed through our platform. This compensation is for news distribution and media services, not for editorial content or coverage decisions. Where Proactive Investors has a commercial relationship with a company covered in this record, that relationship is disclosed within the article. Any such relationship does not determine, influence, or shape the editorial content produced. Where we receive equity compensation, such securities are held independently by a third-party broker and sold at the broker's discretion.
The Site may contain opinions from time to time regarding securities mentioned in other products, including company-related products, and those opinions may differ from those obtained through another Proactive Investors product. Opinions and commentary reflect the views of the named author at the time of writing and are subject to change without notice.
Price and other data is supplied by sources believed to be reliable. Any calculations are made using such data. Neither the data nor the calculations are guaranteed by those sources, by Proactive Investors, by the information providers, or by any other person or entity, and may not be complete or accurate.
From time to time, reference may be made in our marketing materials to previously published articles or opinions. Such references may be selective, may reference only a portion of an article, and are likely not to be current. As markets change continuously, previously published information and data may not be current and should not be relied upon.
FOR OUR FULL DISCLAIMER CLICK HERE