Metals Exploration - La India Development Update
Metals Exploration Plc
3rd Floor,
22a
Email: info@metalsexploration.com
METALS EXPLORATION PLC
La India Development Update
Metals Exploration plc (AIM: MTL) ("Metals Exploration", the "Company" or the "Group"), a gold production, development and exploration company with assets in
Construction and development activities at La India continue to advance ahead of schedule, with overall Project progress standing at 40% complete against a planned 35% at
The Company's recently released construction progress video for La India remains available to view at: https://metalsexploration.com/progress-at-la-india-2/
HIGHLIGHTS:
· Overall Construction Progress - Project construction is 40% complete at the mid-point of
· CAPEX - Total Project expenditure to the end of
· Processing Plant - Construction of the processing plant currently tracking at 13% complete, as planned. Plant foundations are 65% complete, with key concrete footing pours complete or near completion across the crushing, grinding, carbon-in-leach ("CIL") tank and thickener areas. The reclaim tunnel structure is complete. Local contractor Duroblock S.A ("Duroblock") has been awarded the structural, mechanical, piping and electrical installation ("SMPEI") contract alongside Degbed Company Limited ("Degbed") as the specialist mill installation contractor.
· Electrical Infrastructure - The Company has agreed a collaborative arrangement with ENATREL,
· Engineering - Overall engineering is 85% complete, with detailed civil and process designs being progressively issued for construction. Deliverables are now focused on structural, mechanical, piping and electrical installation packages.
· Earthworks and Pre-stripping - Bulk earthworks for the processing plant and run of mine ("ROM") pad areas are 100% complete. Open pit pre-stripping has advanced to approximately 38% complete overall, with pit deforestation fully complete.
· ROM Pad - Approximately 94,800 tonnes of low-grade commissioning ore is now stockpiled on the ROM pad, and this is continuing to build ahead of commissioning. Mine pre-stripping of waste stands at 728,000 tonnes from the two main starter pits of 2026: La India Phase 1 North and La India Phase 1 West.
· Site Infrastructure - Non-process infrastructure is 77% complete, with multiple camp accommodation and administrative buildings now operational. The on-site laboratory building is complete, with Interteck Group plc ("Interteck") appointed to manage laboratory operations.
· Tailings Storage Facility ("TSF") - TSF construction has commenced following contract award to Duroblock, with access road and earthworks activities ongoing.
· Safety & Health - No lost time injuries since construction commenced. The Project recently achieved over 1.2 million hours worked without a lost time injury.
"We are pleased to report continued momentum at La India, where the Project is tracking ahead of schedule at 40% complete against a planned 35% at
"We are particularly pleased to have reached an agreement with ENATREL that delivers the 138kV substation at a fraction of their original proposal, with a collaborative model that saves the Project
"The achievement of over one million hours worked without a lost time injury is a milestone the whole team is proud of, and it reflects the Group-wide safety culture we are fostering at La India. We remain confident in delivering first gold by


Development and Construction Progress
Overall Project construction stands at 40% complete as at
Processing Plant
Civil foundations are 65% complete, with concrete, rebar and formwork activities progressing simultaneously across multiple plant areas. The primary crusher has been installed, the CV02 conveyor is under construction, and the reclaim tunnel structure is complete. In the grinding area, the
The award of the SMPEI installation contract to Duroblock, supported by Degbed for specialised mill installation, marks a significant step in the Project's progression toward the mechanical, piping, and electrical installation phase.
Engineering is 85% complete, with piping isometrics and electrical installation packages the primary remaining deliverables. The elution plant is scheduled to arrive on-site in Q3 2026, with an estimated two-month installation period, and remains on the Project's critical path to completion.
Electrical Infrastructure
The total revised electrical infrastructure budget is
Following negotiations with ENATREL, the Company has agreed a collaborative construction model for the 138kV substation at a total cost of
The La India 34.5kV substation connects to the ENATREL 138kV substation and serves as the primary interface between ENATREL and the processing plant, underground mining and site infrastructure, and incorporating 3 megawatts (MW) of back-up power generation.
The processing plant switch-rooms budget has increased from
Earthworks and Pre-stripping
Bulk earthworks for the processing plant and ROM pad areas are fully complete. Pre-stripping of the La India starter pits Phase 1 North and Phase 1 West have advanced to approximately 38%. The mine haul road is complete, and the west dump access road is also complete.
ROM Pad
Approximately 94,800 tonnes of low-grade commissioning ore is now stockpiled on the ROM pad, representing continued progress toward the 500,000 tonnes ROM stockpile targeted ahead of commissioning. Ore continues to be sourced from pre-stripping and pit development activities.
Site Infrastructure
Non-process infrastructure is 77% complete overall. Multiple camp and administration buildings are now operational, with the most advanced units approaching formal handover. The water and waste treatment plant, constructed by Aquatec S.A ("Aquatec"), is 90% complete and nearing handover following successful hydrotesting. The on-site laboratory building is complete and Interteck has been appointed to manage on-site assaying, which will significantly reduce sample turnaround times from the current approximately eight weeks required for export to
TSF
Construction for the new life of mine TSF has commenced following the award of the construction contract to Duroblock. TSF engineering design is 70% complete, with structural and civil packages being progressively issued. All relevant land has now been purchased.
Health & Safety
The Company is pleased to report no lost time injuries since construction commenced. During the period, the Project achieved the milestone of 1.2 million hours worked without a lost time injury, reflecting the strong safety culture being embedded across all work fronts. Rigorous safety management procedures, including daily pre-shift briefings, job hazard analyses and field-level risk assessments, continue to be applied across all contractor and direct work activities.

For further information, please contact or visit:
|
Metals Exploration PLC |
|
|
Via BlytheRay |
+44 (0) 207 138 3204 |
|
|
|
|
Nominated & Financial Adviser: |
STRAND HANSON LIMITED |
|
|
+44 (0) 207 409 3494 |
|
|
|
|
Joint Broker: |
HANNAM & PARTNERS |
|
|
+44 (0) 207 907 8500 |
|
|
|
|
Joint Broker: |
PANMURE LIBERUM |
|
|
+44 (0) 20 3100 2000 |
|
|
|
|
Public Relations: |
BLYTHERAY |
|
|
+44 (0) 207 138 3204 |
|
|
|
|
Web: |
|
|
X: |
|
|
LinkedIn: |
Registered Office:
RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
Proactive Investors is a publisher of financial news and information. No content in this record, or published on the Proactive Investors website (the "Site"), constitutes a recommendation that any particular security, portfolio of securities, transaction, or investment strategy is suitable or advisable for any specific person. No content is tailored to any specific person's needs, objectives, or financial situation.
Proactive Investors is not a registered investment adviser or broker-dealer and does not provide personalized investment advice. Nothing in this record constitutes investment advice or a recommendation to buy, hold, or sell any security. None of the information providers or their affiliates will advise you personally concerning the nature, potential, advisability, value, or suitability of any particular security, portfolio, transaction, or investment strategy. Any decision to buy, sell, or hold a security should be made only after consulting an appropriately qualified, licensed financial adviser and reading all relevant offering documentation.
This record, and any record we publish by or on behalf of our clients, should not be construed as an offer or solicitation to buy or sell any product or security. Our content is independent financial journalism, produced in a neutral, objective style with full source attribution.
In accordance with the Federal Trade Commission's guidelines on material connections, Proactive Investors discloses the following: we may receive cash or, in some cases, equity compensation from companies whose news is distributed through our platform. This compensation is for news distribution and media services, not for editorial content or coverage decisions. Where Proactive Investors has a commercial relationship with a company covered in this record, that relationship is disclosed within the article. Any such relationship does not determine, influence, or shape the editorial content produced. Where we receive equity compensation, such securities are held independently by a third-party broker and sold at the broker's discretion.
The Site may contain opinions from time to time regarding securities mentioned in other products, including company-related products, and those opinions may differ from those obtained through another Proactive Investors product. Opinions and commentary reflect the views of the named author at the time of writing and are subject to change without notice.
Price and other data is supplied by sources believed to be reliable. Any calculations are made using such data. Neither the data nor the calculations are guaranteed by those sources, by Proactive Investors, by the information providers, or by any other person or entity, and may not be complete or accurate.
From time to time, reference may be made in our marketing materials to previously published articles or opinions. Such references may be selective, may reference only a portion of an article, and are likely not to be current. As markets change continuously, previously published information and data may not be current and should not be relied upon.
FOR OUR FULL DISCLAIMER CLICK HERE