PetroNeft puts Arbuzovskoye 106 well into production
Last updated: 06:11 18 Dec 2014 EST, First published: 07:11 18 Dec 2014 EST
PetroNeft (LON:PTR) has brought the Arbuzovskoye 106 well into production following drilling success.
The company said the well encountered oil in an upper Jurassic reservoir at a depth of 2,465 metres, and flowed oil at a rate of 170 barrels oil equivalent.
It exceeds pre-drill expectations for 100 to 150 barrels per day.
Drilling is now underway for the 103 well, the latest and most southerly well to date.
Elsewhere horizontal drilling in the Tungolskoye No. 5 well is slower than expected, and the company said it expects results in January. The company added that its contracted terms for the programme mean there will not be additional costs due to the delay.
The Sibkrayevskoye 373 well is expected to start in February, and the company said the drill rig is now being erected. In the meantime a seismic programme is underway, though the main data acquisition will occur in the first quarter of next year. Full results from the seismic programme are anticipated in the third quarter.
The company added that costs and capex reductions, as a result of the Russian Rouble's decline against the US dollar, have acted as "a natural hedge" to falling oil prices.
"I'm very pleased with the rate achieved from the first new well drilled at Arbuzovskoye since February 2013 and look forward to updating shareholders with the results of the additional wells at Arbuzovskoye," said chief executive Dennis Francis.
"The pilot hole at Tungolskoye has achieved its objectives in confirming the structure, net pay and oil flow and we look forward to the production test result from our first horizontal well in the New Year"